Cosinus Slide® Joint
The Cosinus Slide® armour concrete floor joint is by far the strongest armoured joint for concrete industrial floors. Invented in 2012, the Cosinus Slide® is a smart investment in the future of your industrial floor.
Technical data videosThe appropriate choice for a construction joint is always a function of engineering and calculations for load transfer. Please chose whether you want to run a pre-calculation yourself with our online tool or if you want us to provide you with a complete and free-of-charge design check.
Documentation

Communication on the European patent No. 2729619 and No. 2027340.
We are pleased to announce that on 06/05/2015 the European
Patent Office has decided to grant a European patent no. 2729619 based on the
European patent application EP13708716 directed to the Cosinus Slide joint and
on 13/05/2015 decided to grant the European patent no. 2027340 based on
European patent application EP06754306 addressed to the Sinus Slide joint
solution in general. With these decisions, the European Patent Office
recognizes HCJ's innovative solutions in construction joints for industrial
floors.
Why Cosinus Slide®?
First and most visible: It has the only and unique "double slide" continuous load transfer on the market. The famous sinus wave shape on top of the floor avoids vibrations and neutralizes wheel impact. Second, less visible, yet most important: It has the only and unique "double sinus slide" continuous load transfer system on the market. A second sinus wave in the middle of the floor, in combination with the continuous 3D anchorage system, creates the best performing and highly efficient load transfer system over and throughout the joint. It achieves this without using the limited performance of dowel technology from inferior copies
As a result of combining these two advantages:
- Best Load-transfer system: no limitation on where you place your racking system
- Decreased floor thickness, while maintaining the strength
- Optimal operational efficiency
- Less expense in the future on armoured joints and concrete floor maintenance
- Less expense in the future on warehouse equipment maintenance (forklift, robots, manual forklift, hand pallet jack)
- Continuous 3D anchorage system (patented technology)
- High level of comfort experienced by forklift operators
- Avoids production downtime during concrete floor maintenance.
Construction joint and industrial floor conditions after many years

Profile height
h
|
max. profile height
w
|
Profile length
l
|
Sinus
a
|
Cosinus
b
|
Slab thickness
t
|
Adjustable steel plate
c
|
Weight per profile
|
Weight per meter
|
---|---|---|---|---|---|---|---|---|
90 | 120 | 2,60 m | 50 | 35 | 90-120 | 40 | 25,85 | 9,94 |
115 | 150 | 2,60 m | 60 | 50 | 115-150 | 50 | 30,99 | 11,92 |
160 | 215 | 2,60 m | 80 | 75 | 160-215 | 75 | 39,42 | 15,16 |
205 | 300 | 2,60 m | 80 | 120 | 205-300 | 120 | 45,76 | 17,60 |
300 | 400 | 2,60 m | 116 | 170 | 300-400 | 170 | 61,67 | 23,72 |
*